Completed project

Waterbeck

Farmland reinstatement after water infrastructure works

We carried out agricultural reinstatement after river-crossing works at Waterbeck, handling and placing topsoil to the finish agreed with the farmer and project team.

01 / THE JOB

Site requirements.

The reinstatement area included an existing pipeline and drainage, with a nearby watercourse setting a further working constraint. Before moving soil, we agreed the working limits, topsoil source and haul route with the farmer and project team.

02 / OUR WORK

Our scope.

We excavated, loaded and hauled topsoil, then spread and profiled it across the agreed areas. We cleared stones from the pipeline area before topsoiling and topped up existing drains with gravel.

03 / ON SITE

Construction approach.

  • The existing pipeline alignment was marked out and avoided during the work.
  • Topsoil movement and placement stayed within the agreed working limits, protecting the existing drainage.
  • Spreading and profiling brought the disturbed land back to the agreed surface finish.
  • The remaining land was left undisturbed, with the agreed clearance maintained from the watercourse.

04 / THE RESULT

The result

The ground was reinstated to the finish agreed with the farmer and project team on site, with the existing pipeline and drainage protected.

LET’S TALK

Have a job in mind?

Tell us the location, the work needed and your timescale.

07802 761238