01 / THE JOB
Site requirements.
The reinstatement area included an existing pipeline and drainage, with a nearby watercourse setting a further working constraint. Before moving soil, we agreed the working limits, topsoil source and haul route with the farmer and project team.
02 / OUR WORK
Our scope.
We excavated, loaded and hauled topsoil, then spread and profiled it across the agreed areas. We cleared stones from the pipeline area before topsoiling and topped up existing drains with gravel.
03 / ON SITE
Construction approach.
- The existing pipeline alignment was marked out and avoided during the work.
- Topsoil movement and placement stayed within the agreed working limits, protecting the existing drainage.
- Spreading and profiling brought the disturbed land back to the agreed surface finish.
- The remaining land was left undisturbed, with the agreed clearance maintained from the watercourse.
04 / THE RESULT
The result
The ground was reinstated to the finish agreed with the farmer and project team on site, with the existing pipeline and drainage protected.